Wrapping up.

Wow!  I did not realize how long it has been since posting. All the interior cabinetry  and floors are completed. The fire sprinkler system is completed and alarmed. The electrical and lighting is all completed. We also completed the steel framing and aluminum decking. The front entry is done, and the driveway and all the approaches are repaved. We had a pre-final inspection, and there are only a few things to complete before we can occupy the structure. So here are some pics of all the latest work.

The deck. This was a big thing. All the planning and calculations and hoping we had ordered a sufficient amount of material. We had attached the ledgers prior to stuccoing the exterior. It was like building a big erector set (I may be dating myself there).

steel joists and ledger for 2nd floor

The  framing:

completed deck framing

Once that was done it was off to LA to pick up the decking material. Our choice was called TB-940 safe-t-grid from McNichols Co.  We wanted to minimize maintenance and also needed a minimum weight bearing capacity of 200lbs. per square foot for the second floor deck. Using steel box beams for joists and the aluminum deck we have a capacity of around 1000 lbs. per square foot. The shipping was very expensive so we borrowed a trailer and picked up the decking ourselves.

Aluminum decking strapped down and ready for the long ride home.

All the decking is pre-cut to fit your square footage of deck so there is basically no cut off or waste.

first floor deck

and second floor deck with cross-bracing:

These are the stair treads.

You can now see the reason for the weight bearing capacity, we moved a hot tub onto the upper deck. Once the stairs and guardrails are installed we can get final inspection. Yay!

In the meantime we also completed some other items:

We finished the front entry area by adding a step and using the left over pavers from the patio.

Front steps and pavers and a curved planter in front of the house

We repaved the driveway approach and patched all the cut outs in the driveway.

Approach and curbing.

Don’t mess with a woman and her steamroller!

And here are the completed bamboo floors:

So we are still busy every day with the final steps. There are a million small details that need completing as we go along and we are just a few weeks away from occupancy!

Finish Work

Well, it has been a prodigiously long time since I updated any pictures and much has happened.  Once the plastering was completed and the front door set, we took a little break and spent a month in France! We visited friends and relatives and bicycled all over the Loire Valley and in the south of France. It was fantastic to get away from work although I didn’t know how much we needed a break.  We rode along the Loire river through small villages on the way to Chenonceau and all the stress seemed to melt away. Oh, and did I mention that if you ride every day….then you can eat everything in sight!  Which is pretty much what we did.

Pastry in Chinon…..

Bike trail to Chenonceau

further south

When we returned, it was right back to work on the house. We set all the cabinets in the kitchen, laundry room and bathrooms…

counters, hood and ’52 Wedgewood ready to go.

a larger oven and a dishwasher! (our first)

the bamboo butcher block in progress

laundry room

One thing we have always enjoyed are glass awnings. When I was growing up, many of the art deco buildings in Pasadena had glass awnings with the wired safety glass in them. On my first trip to France I was thrilled to see so many glass awnings and swore if I ever got the chance to build one I would. I was able to find some trick hardware from CR Laurance for a modern awning and we powder coated our roof panel lifting plates and attached them to the wall as anchor points. We had to use 9/16″ safety glass and it was tricky to get it up and in place, but we are really happy with the results.

This is our modern  glass awning. We chose blue glass, which  looks the best with our building.

We also installed all the cabinets in the bathrooms and the fixtures:

Floating cabinets and a vessel sink from China. The sink was a gift from Ariane’s good friend Marie who did a ceramics artist in residency there.

 sink interior

Bathroom with glass shower installed

Ariane and I are now busy laying the floors upstairs.

bamboo floor in closet

Almost finished with the master bedroom Most all of the electrical outlets are functional, all but a few of the lights are installed, and the sound system is working so we can listen to music in each room.

Our fabulous foyer light fixture, the moon of Meepzorp

A wall sconce made by Barry Frantz looks terrific.

We continue to plod along every day, trying to get out of our trailer before Christmas!

We have been so busy, I had to bypass the posting on the plastering process…which is probably ok as it was a long and difficult process. More so for the plasterers, as we were all operating on some bad information and they had to figure a lot of things out as they went. I cannot say how much we appreciate all the good work done by  Felipe Landin and his crew,  Luis and Marcelo, of Mission Plastering. Great work and attention to detail and we highly recommend them.

Marcelo and Luis

Hallway

Living room

We installed copper backsplashes and then the kitchen cabinets. Pacific Heating of Morro Bay made all the backsplashes. Green Goods of San Luis Obispo made the cabinets and they did an excellent job, excellent quality.

Island cabinets

the tape is where the hood will mount on the backsplash

A few more drawers and doors to set and then the countertops!

And finally some really good news!  Our front door finally arrived and we made quick work of getting it in. Now the house is completely closed, and Felipe will stucco it this week!

building a house requires a daily infusion of red wine!

Milano door installed and ready for the stucco.

The door will look good from the inside

Entry door, and an art piece by Christina McPhee.

We cleaned up the floors upstairs and now you can see what the bathroom is going to look like:

Much of the electrical finish and plumbing has been completed. The utility room is completed and so has the laundry room. So we are left with setting bathroom cabinets and fixtures, stairs, upstairs flooring and  the decks.  Just a brief update, but we are getting it done.

It has been another long time since the last post because most of what we have been doing is drudgery. We installed all the interior sheetrock, and taped and mudded it before the plasterers could come in. We figured it was a lot less expensive to fill gaps with tape and mud than with plaster…. it took about 15 boxes of mud. We then restained the floor with some more black, and last week we sealed and lacquered the floor.

kitchen wall mudded and ready for plaster

kitchen wall with floating shelves

wall for stove, with floating bamboo shelves

I also got to turn to some finish work. We found some cool looking vent covers for the dryer and the ceiling fan in the laundry room and I installed those.

dryer vent on the left. the cat door needed a cover so I made some out of aluminum sheet and installed them on the cat doors.

Laundry room vent cover

While I have been doing this, Ariane has been oiling the cabinet doors with tung oil. We took some of the doors to the glass company for inserting glass and they should be back this week.

We did not like the look of the vents for the central vac system and I was able to adapt a diffuser from Seiho Co. to cover the exhaust vents instead and keep up the semi-industrial look of the structure.

Diffusers mounted over the exhaust for the vacuum.

Most of the exterior lights have been installed so the outside is getting finished. The plasterers have started on the inside and the plaster is looking good!

Office ceiling plastered and drying...muy liso!

Felipe and Luis plastering the office!

Filipe plastering the office wall

Felipe plastering the office wall

Luis plastering

Felipe did not have experience working with Biolime, but he was able to get familiar with the product very quickly. He has done a terrific job on the stucco and now on the plaster as well.

We will soon be setting the cabinets and installing the fixtures.  yeah!

Color Coat Completed !

Well, all completed with the exception of the front door entry as we are STILL waiting for the arrival of the front door!  But the stucco crew really got after it and got the rest of the house done in about 3 days! Here is the finished product.

Applying the color coat

Once they finished, they removed all the scaffolding and it looks nice and clean around the house for the first time in a long time!

Steps to nowhere. This is where the deck is going to go.

the guest bathroom in front!

We are going to put a glass awning over the door, that is what the hardware is for. We liked all the glass awnings we saw in Europe.

So we have the sheetrock mostly completed and we will be ready to plaster the inside very soon. We spent the day laying out the kitchen cabinets for installation soon. There is a little bit of light showing at the end of the tunnel. I can’t wait to get back to the banjo workshop! I have tons of new ideas based on some things I learned during this project.

We have been working 7 days a week for several weeks now, and have literally had no extra time to post any updates until now. We are taking Sat. and Sun. off  this weekend, so I can post up progress. First of all, the house is all dried-in will all the doors installed except  the front door which is now long overdue. The two base stucco coats are completed on the outside, with the exception of two places where we needed to put doors. The electrical, and low-voltage is installed and completed. Plumbing is done and everything has passed inspection. We installed the sheetrock everywhere except the master bedroom and closet, because the tile setter is working in there. The stove chimney is installed and when it recently rained…..no leaks anywhere! So here are the updated pictures.

Looks more like a house now.....

They did a real good job around the windows and doors…

All the edges are rounded to run water away from the window

Same for the doors.

All exterior doors are steel, the hole to the left is a cat door....

We were able to use 3 doors that were seconds on the outside, two silver powder-coated  and they happened to have a blue powder-coated one that was an odd size. Luckily for us it fit the back entrance, so we had to have it!

Fortunately we share the same eclectic taste.

So with three silver doors and one blue door….when it came time for a steel utility room door, naturally we needed to powder-coat it as well. Ariane wanted a red door, and boy did we get a red door. We had it powder-coated candy apple red! It was a bear to install but it came out pretty nice!

Sorry the plank is in the way, but I was too lazy to move it for the picture.

With the house closed in, we started sheet rocking it to get it ready for plastering. I am not a big fan of sheet rocking it is dirty, dusty and a ton of overhead work…. but we did get it mostly done and it really makes the house look good inside.

Green boarding the guest bath....

Entry with art piece

still waiting for that front door….. to the left of this photo.

Living room

Kitchen

Oh yeah, I forgot to mention, we installed the solar hot water collectors and ran all the feeds down to the utility room, installed a central vac system, acid stained the concrete floors and  insulated all the interior walls for sound before we sheet rocked.

My friend Kelly Cannon is a master tile setter and he is doing the bathrooms!  They are coming out beautiful!

master bathroom

The large tiles are really difficult to install correctly, not a job I would want to tackle.

Lastly, we added a patio area right off the decks, when we discovered the deck area was not large enough. Andy DeVillers and his crew did a fantastic job as always.

The pavers will allow water to drain through and water the trees.

We are going to use steel for the deck framing and aluminum planking.  Clay Newman, of Alaska Welding, is fabricating the steel posts and beams to support the decks. He fabricated the front entry steel. They will be powder-coated the same at the front entry. His work is outstanding and his vast experience really shows with the practical suggestions he makes as well as the meticulous preparation he does before fabricating.

So that is it for now.

 

Half-wrapped!

Things are starting to speed up now!  The plumbing is all done and the electricity will be done soon. This involves about a million decisions on lights, plugs, switches, and generally trying to figure out all the potential future needs and installations…..yikes. Ariane has been up to the task on the lighting and is handling that crucial aspect. Meanwhile, we set the ledgers for the upper and lower decks and started running the metal roofing panels. The plasterer Felipe is barreling through and has the first story wrapped in paper and wire for stucco. He will be back Monday with a crew to set all the scaffolding for getting the whole thing wrapped… a huge undertaking. I have a crew coming on Monday to help us with the roofing and we should have that done next week, then the whole thing will be completely waterproof….yeah!

So here are some updated pictures:

East side wrapping

South side , with first roof panels installed!

The roofing should go fast, each panel is 38″ wide and after overlapping, you cover a 3′ by whatever length the roof is with one piece…sweet!  Metal roofs are great, they do not have the thermal mass of shingles or tiles which radiate  heat back into the structure, so you stay cooler in summer, warmer in winter. Plus with baked on finish the metal roof lasts 40 yrs. The underlayment is special too as it is also rated for 40 yrs, unlike felt paper which is about 15. So you end up with a pretty maintenance free roof for a  long time.

You lay the roof panels on so the overlap faces away from the main direction of rain and bad weather. In our case that is from the northwest, so all the overlaps face east.

The installation of electricity and plumbing is unique for these structures as well, here are some details.

You have to block out areas where plumbing goes like this. The red spray paint marks the electrical chases. To pull wire or move it through the chases, you can make a 4" hole and then feed wire.

Fire sprinkler riser.....

Here you can see a switch box and the circle cut for feeding wire to a light outlet..

Here are some random photos of the interior space:

Ariane, James and I built the stairs!...no more ladders!

Office with clerestory windows.

Upstairs bedroom.

Hallway, and light cans